Unanswered Questions · 9 of 15

The upgrades pricing model

What will Hydro-Québec pay for the extra power from the Churchill Falls upgrades? NL Hydro says the pricing model exists. Will it be made public?

Why it matters

The upgrades add about 1,275 MW and are priced on a cost-plus formula with a declining revenue requirement. The House voted without seeing the numbers.

What’s at stake

About $4.8 billion of recoverable capital (about $5.5 billion before the $700 million carve-out)

Who can answer

NL Hydro. Find your MHA at assembly.nl.ca.

Status

Promised in the House on September 16. Not tabled before the September 17 vote.

Sources

DCIA Section 6(f); Hansard, Sept 16 (Mr. Ladha), Sept 17 (Mr. Parsons)

Answers to date

None yet. Got an answer? Use the form below.

Send an answer

Got a reply from an MHA or Minister? Send it here. Dr. May checks every submission before anything is published or the status changes. Only the MHA's or Minister's answer is published, never your own details.

All 15 unanswered questions